Tuesday, May 20, 2014

Last of Gas Pipeline Arrives from India

Francisco Labastida Gomez, General Coordinator of Strategic Projects for Sinaloa, said that the last of the pipeline needed for construction of the natural gas pipeline to Mazatlán has arrived.
The 8,636 pieces of pipeline began to be offloaded at Mazatlán’s docks on Sunday for the North-Northwest pipeline.
The pieces of pipeline for the project began arriving last October and the Sunday delivery brought the total number of pipeline segments to 28,235.
The pipe will be sent to a holding area in Guasave, where it will be disbursed, as needed for the construction of the pipeline from El Fuerte to Mazatlán.
(from Noroeste)